Our preventative maintenance team attended a central London office building to
Remove all 5 existing hatches.
Install new MF ceiling where it has been cut out.
Install new 100mm insulation where the old has been removed.
Plasterboard using 15mm soundboard and 12.5mm plasterboard to match the existing.
Cut out plasterboard and install 5 new 1200mm x 600mm access hatches.
RECENT JOBS
Replacement concrete bollards
Our groundworks team attended a Midlands industrial estate in order to repair damaged concrete bollards.
Fire door replacement
Our reactive maintenance team attended a West End office building in order to replace a fire door.
Block paving repair
Our groundworks team attended an office centre after a number of heavy goods vehicles had damaged the block paving.
Repair of brickwork
Our reactive maintenance team attended a business centre in order to repair a damaged wall.
Replacement glass unit to office conservatory
Our planned maintenance team attended a commercial office in order to replace the damaged glazing on an internal conservatory.
Access door repair
Floor spring and bottom shoe replacement of door