2 man team to attend site to carry out the following:
To lift out raised block paving in areas specified by Health and safety report in 3 areas
Set aside while roots are cut out and remove. Install sand to level base out
Relay blocks ensuring all level
Go over areas with wacker plate
Reset yellow bollard Dig out rodding eye
Supply and install new rodding eye Remove all waste from site
RECENT JOBS
New street lights
Electrical installation team fitted 3 new 6 meter street lights in commercial office car park with LEDs. This included groundwork in order to install new electrical cabling for the lights.
Installation palisade fence
Planned maintenance team installed a fabricated palisade fence at an industrial site in order to enhance the security of the site.
Installation Aco drain
Groundworks team installed removed existing damaged drainage channel and installed new ACO drain.
Refurbishment of Fire Escape
As part of a planned maintenance schedule in response to a Fire Risk Assessment we cleaned , applied non slip finish , highlighted nosings, painted fire door and applied D-handle to fire escape and fire exit.
Door Frame Repair
Our carpentry team responded to a reactive maintenance request to repair the door frame of the ladies toilets in an office building.
Fitting of Hand Dryer
Fitting of a new hand dryer in ladies tiles of office as part of a refurbishment.